Category Archives: PMP Exam Question Practice

PMP Practice Exam Questions and Answers | Scenario-Based! | 30

– See all the PMP Exam Questions – 

PMP Exam Question Session 30

Scenario-based questions, just like the real PMP exam!

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

Watch the video below for the questions and answers! 

Question 1

You are working on a project and it has become apparent that part of the product your company was creating they won’t be able to complete. You decide to outsource it to a vendor, and offer a bonus to the vendor if the work is completed in two months. What type of contract will you use?

A)  CPFF (Cost plus fixed fee)
B)  FPWEA (Fixed price with economic price adjustments)
C)  T & M (Time and materials)
D)  FPIF (Fixed price incentive fee)

Question 2

You are working on the schedule of your project and have just created a schedule network diagram. You have noted the duration, early start and early finish dates for each activity. What will you do next?

A)  Perform a “forward pass”, noting the Late Start and Late Finish for each activity.
B)  Perform a “backward pass”, noting the Late Start and Late Finish for each activity
C)  Break down the scope into smaller work packages you can assign to your teams
D)  Perform a “backward pass”, noting the float and positions of each activity

Question 3

You are working on a project that is outsourcing part of development to a third party. Your project sponsor wants to keep the risk to the organisation low. What sort of contract will you use to outsource this work?

A)  CPFF (Cost plus fixed fee)
B)  T & M (Time and Material)
C)  FFP (Firm Fixed Price Contract)
D)  CPIF (Cost plus Incentive fee)

Question 4

You have acquired your project team, and are ready to distribute the work to your team for them to begin. You will use your project’s outlined work authorisation system, which:

A)  Manages the timing and sequence of when activities need to be performed, and by whom.
B)  Tracks and manages work defects as they arise
C)  Identifies the resources needed to complete activities
D)  Is used for comparing actual work against the baselines

Question 5

You are managing a project to build a new meeting hall. Half way through, one of the stakeholders advises the stage is not big enough, it must be twice as big. This was not originally planned for. What will you do next?

A)  Get the work done immediately and start executing
B)  Update the impacted baselines – scope , cost and schedule
C)  Update the work performance reports and share with stakeholders
D)  Analyse the impact to the cost , schedule and scope, then submit the change request to the change control board for approval.

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | Scenario-Based! | 29

– See all the PMP Exam Questions – 

PMP Exam Question Session 29

Scenario-based questions, just like the real PMP exam!

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

Watch the video below for the questions and answers! 

Question 1

You are in the process of creating the Scope Baseline of your project and have broken the high level features into assignable work packages. What will you do next?

A)  Create a Schedule Network Diagram to show where those work packages will fit in your project schedule
B)  Create an Activity List of activities needed to complete the work packages
C)  Assign the work packages to people on a first come, first served basis.
D)  Create the WBS Dictionary, and assign each activity a unique identifier, acceptance criteria and milestones.

Question 2

Your project is about three fourths done when the site engineer reports that due to inherent complexities a certain deliverable will be delayed as they work through the solution. He makes a request for this new work to be added to the scope and schedule of your project. You work with the engineer to analyse the impact of this change to cost, and write up a change request for approval from change control board. They have approved the change. What will you do next?

A)  Start work immediately, you shouldn’t delay any further
B)  Determine the impact of this change to scope , schedule and cost before making any change
C)  Perform Quality Assurance on the change, so it doesn’t happen again
D)  Before implementing the change, update the scope and schedule baseline and note the approved change in the change log.

Question 3

You are in reviewing the defect list with your project team and have found that many of the issues could have been prevented by using a simple code review checklist. You prepare a code review checklist and ensure the code is reviewed as per the checklist. This is called:

A)  Preventive Action
B)  Corrective Action
C)  Defect Repair
D)  Quality Control

Question 4

Your team is performing quality inspection and testing of the product, and some defects have been raised. Because they are small, the quality manager wants to just fix them immediately and keep quality testing – she doesn’t want to have to make extra paperwork. What will you do next?

A)  Ask your quality manager to fix the defects quickly and move on, so there is no delay
B)  Ask your quality manager to calculate the adjustments to schedule and cost and update the project management plan
C)  Analyse the impact to cost and schedule, then ask your quality manager to raise a change request for the change to the product.
D)  Remove the items from the project. If they are no longer in scope, no paperwork is needed.

Question 5

You are a project manager working closely with the customers of the project. During one conversation, a key customer executive mentioned they will need a particular feature not mentioned in the project scope statement. What should you do next?

A)  Explain the change procedure and ask them to submit a request for change
B)  Add the additional requirements to the project plan – the customer is most important.
C)  Go ahead and create the main features and then see if the customer still wants the extra feature when they see it.
D)  Discuss the feature with the other customer representatives to see if they change their mind.

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | Scenario-Based! | 28

– See all the PMP Exam Questions – 

PMP Exam Question Session 28

Scenario-based questions, just like the real PMP exam!

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

Watch the video below for the questions and answers! 

Question 1

You are working through your project and performing quality inspections on the product. During inspection, a key part of the product was found defective. This was not planned for, and the team brainstormed and managed to make the product work without the defective component. This is:

A)  Risk mitigation
B)  Transfer of risk
C)  Risk avoidance
D)  Work-around

Question 2

You have a problem in the project you are working on, where a group of stakeholders from one part of the business are not receptive to the change brought on by your project. What is the best approach to resolve this conflict to assure longer lasting resolution?

A)  Smoothing or accommodating them
B)  Collaborating or problem solving with them
C)  Compromising or reconciling with them
D)  Forcing or directing them

Question 3

You are working on a new parkland project in New Zealand, where heavy earthquakes have been known to occur. You meet with your project sponsor and risk team, and agree on an action to “Transfer the risk.” What will you do next?

A)  Ask the executive team to change project sponsors, so your current sponsor is not exposed to the risk.
B)  Purchase insurance for earthquakes to transfer the risk to another company.
C)  Form a shell company to transfer the risk of liability to, if anything bad happens.
D)  Transfer the risk to the people using the park, by placing a “Caution” sign out front.

Question 4

You are working with the quality manager in your project, where your product has limited features in order to reduce the price, but you still want it to work well and correctly. The quality manager has asked you for advice on the quality and grade of the product. What will you tell her?

A)  Bad quality is acceptable, but bad grade is not
B)  Bad grade is acceptable, but bad quality is not
C)  Neither bad grade nor quality is acceptable
D)  Grade and quality are the same thing

Question 5

You are speaking with the quality manager of your project, and he has suggested a quality approach for the quality management plan process that was made popular by Deming. What is he referring to?

A)  Apply continuous small improvements to reduce costs and ensure consistency
B)  Perform inspections on every product that is made
C)  X and Y Theory – only hire Y type workers as they are highly engaged
D)  Plan-do-check-act to improve quality iteratively

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | Scenario-Based! | 27

– See all the PMP Exam Questions – 

PMP Exam Question Session 27

Scenario-based questions, just like the real PMP exam!

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

Watch the video below for the questions and answers! 

Question 1

Your project sponsor has asked for an update so she can advise her executive team on the project progress. What will you tell her if your project has an EV of $98,000, PV of $90,000 and AC of $85,000? You are:

A)  Ahead of planned schedule and under budget
B)  Behind planned schedule and under budget
C)  Ahead of planned schedule and over budget
D)  Behind schedule and over budget

Question 2

The Estimate at Completion (EAC) is the forecast cost of the project once finished. Your project has a budget of $100,000, and 30% of the work has been completed against 40% planned. You have spent $40,000 so far. If future work will be accomplished at the planned rate, Estimate At Completion (EAC) would be:

A)  $90,000
B)  $140,000
C)  $70,000
D)  $110,000

Question 3

You have gathered the requirements and scope for your project, broken them down into work packages for your project teams and then into activities that need to be completed and scheduled. What will you use to find the minimum duration for your project, and any flexibility you have between activities?

A)  Qualitative analysis
B)  Critical path method
C)  Resource leveling
D)  Variance analysis

Question 4

You are in charge of a new building project where the project plan is in place and work is currently in progress. A critical concreting task is coming up in the next three months. Your company employs concreters specifically for this type of work. When asking them about their availability they do not wish to commit and cannot give a straight answer. What should you do next?

A)  Review the project milestone list and put concreting later in the project to allow you time to get the right people.
B)  Review the issue register and raise the lack of resources in the issue log.
C)  Review the project scope and remove concreting for now to avoid the conflict.
D)  Review the project resource calendars regarding their availability, then have the right conversation with their leader to bring them on board at the right time.

Question 5

You are working through the schedule for your project after gathering the requirements, scope, breaking them down into work packages and then activities. You now need to estimate how long each activity will take, so you can place them in your Gantt Chart. What should you do next?

A)  Use your best guess for each and estimate for each activity so you can complete your Gantt Chart quickly
B)  Involve people who will be doing the work to get estimates
C)  Ask your boss to estimate, that way they will have to explain if it’s wrong
D)  Write down each activity time without buffers – it will look more accurate this way

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 26

– See all the PMP Exam Questions – 

PMP Exam Question Session 26

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

Watch the video below for the questions and answers! 

Question 1

You have just validated the last piece of scope for the product you are delivering, with your stakeholders and gained their sign off. You have released the resources working with you back to their normal areas. What will you do next?

A)  List all the stakeholders for your project
B)  Create a project management plan
C)  Oversee the testing of the product to ensure its quality
D)  Write a Final Report summarising the performance of the project

Question 2

As a project manager, you are working on an activity that develops a document that formally authorizes the existence of a project. What will you do next?

A)  Identify the Stakeholders and list them in the stakeholder register
B)  Gather and acquire the Project Team
C)  Plan the costs of your project in detail
D)  Plan the schedule of your project

Question 3

A project management plan is a formal approved document that defines how the project is executed, monitored and controlled. Who is responsible for the project management plan?

A)  The Program Manager
B)  The Project Manager
C)  The Project Sponsor
D)  The Project Team

Question 4

You are working on your project management plan and quality management plan with your quality team leader. Your quality team leader wants to review the Cost of Quality (CoQ), and asks you for advice on what to include. Out of his list, which costs would you NOT consider?

A)  The cost of your project team (resources)
B)  The cost of preventing defects
C)  Appraisal costs
D)  Failure costs

Question 5

The To Complete Performance Index is the rate that future project work must be performed at. Your current project has a BAC of $100,000, EV of $50,000, and AC of $40,000. What is the rate of work we must achieve (To Complete Performance Index)?

A)  0.55
B)  0.83
C)  0.44
D)  1.16

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 25

– See all the PMP Exam Questions – 

PMP Exam Question Session 25

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

Communication Channels are the number of communication paths among the team members working on the project. For a project with a team of 3 people, the total number of communication channels would be:

A)  3
B)  5
C)  2
D)  4

Question 2

You are scheduling a meeting with your project team to share their viewpoints and expertise in the project work. Which of the following is NOT one of the rules of effective Meetings?

A)  Schedule recurring meetings in advance
B)  Set a time limit and keep to it
C)  Ensure flexible time limits
D)  Stick to the agenda

Question 3

You need to make a decision with your project team on how to move forward with a particular feature. You decide to take a vote, but you need to know how to ensure the outcome is valid. Which of the following is NOT one of the types of Group Decision Making Techniques?

A)  Unanimity
B)  Majority
C)  Plurality
D)  Duopoly

Question 4

You have hired a Business Analyst specifically for your project, and have asked them to create a plan of how the project will document, record and manage all the requirements. What are you asking them for?

A)  Scope Management Plan
B)  Requirements Management Plan
C)  Integration Management Plan
D)  Resource Management Plan

Question 5

The Scope Statement of your project provides a baseline of the project’s scope and deliverables and the work required for all stakeholders to see. Which of the following is NOT one of the elements of a Project Scope Statement?

A)  Project scope description
B)  Acceptance criteria
C)  Project Selection
D)  Project Assumptions

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 24

– See all the PMP Exam Questions – 

PMP Exam Question Session 24

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

As a project manager, you understand the importance of interpersonal skills to enhance the probability of project success. Which of the following is NOT one of the types of project manager’s interpersonal skills?

A)  Team building
B)  Dictating
C)  Leadership
D)  Communication

Question 2

You are working on a new feature in your project and need to estimate the cost to complete it. You have the work packages from the lowest level of your work breakdown structure and the teams have all given their estimate to complete their parts. What estimation technique will you use for the total feature estimate?

A)  Parametric estimating
B)  Bottom-up estimating
C)  3 point estimating
D)  Analogous estimating

Question 3

You are working with a project sponsor who has a thorough understanding of motivating individuals. What is the third-level need of Maslow’s Hierarchy after physical needs and security?

A)  Social Needs
B)  Self-Actualization
C)  Business Need
D)  Personal Needs

Question 4

You are a project manager working in manufacturing and you need to estimate the resources you will need for the next phase of your project. What is a fast estimation technique that uses data from past projects for an activity that is very similar in nature for cost or duration?

A)  Related Estimating
B)  Parallel Estimating
C)  Analogous Estimating
D)  Comparable Estimating

Question 5

As an effective project manager, you understand the importance of actively communicating with your team members. What would be something you will do above everything else when communicating to others?

A)  Speaking
B)  Listening
C)  Mentoring
D)  Helping

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 23

– See all the PMP Exam Questions – 

PMP Exam Question Session 23

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

You are identifying the stakeholders in your project and need to analyse their engagement with a stakeholder engagement matrix. Which of the following is one of the types of Stakeholders?

A)  Executive
B)  Resistant
C)  Sensitive
D)  Passive

Question 2

You are working on managing stakeholder relationships in a project and identifying the stakeholders. What is something you will use as an input to this work?

A)  Work performance reports
B)  Change requests
C)  Approved change requests
D)  Agreements

Question 3

You have taken over a software development project 10 months after it started, and need to find out project stakeholders and roles. Which one of the following documents will provide the list of the project stakeholder to you?

A)  Project Management Plan
B)  Stakeholder List
C)  Stakeholder Register
D)  Identify Stakeholders

Question 4

There are many stakeholders in your project and you need to find out who is most likely to go above and beyond to help you. In your stakeholder analysis, what type of stakeholder are you looking for?

A)  Mature
B)  Saturated
C)  Superficial
D)  Leading

Question 5

You are working on a new project where the team is not working well together. You understand this as one of the five stages of team development that you will have to work through. Which of the following is NOT one of the stages of Team Development?

A)  Forming
B)  Initiating
C)  Storming
D)  Adjourning

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 22

– See all the PMP Exam Questions – 

PMP Exam Question Session 22

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

You are arranging a third party to perform work for your project. You are creating a document outlining the details of the work to be completed and the time-frame it needs to be delivered in. This is called the procurement:

A)  Obtainment Of Work
B)  Recovery Of Work
C)  Statement of Work
D)  Executive Work

Question 2

What is the type of contract when an expert is hired to complete a particular portion of the project for $120 per hour, plus their materials?

A)  Fixed fee
B)  Time and materials
C)  Cost plus fixed fee
D)  Cost plus incentive fee

Question 3

You are a project manager working on a telecommunications project where a portion of the work has been completed by a vendor outside your project. What is it called when your team makes a review of the procurement process?

A)  Audits
B)  Inspection
C)  Quality Check
D)  Review

Question 4

You are starting a project with a project charter and the next major process is to identify all the relevant stakeholders for your project. Which one of the following is used to perform stakeholder analysis?

A)  Stakeholder Analysis Model
B)  Maslow’s Hierarchy of Needs
C)  Salience Model
D)  SWOT Analysis

Question 5

You are working as a project manager in the health sector where a stakeholder raises a proposal for modification to the scope of the project. What should you tell them to do?

A)  Raise an issue in the issue log
B)  Go head and change the scope themselves
C)  Raise a change request that will go through the CCB
D)  Raise their idea at the next retrospective

– See all the PMP Exam Questions – 

PMP Practice Exam Questions and Answers | 20

– See all the PMP Exam Questions – 

PMP Exam Question Session 20

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

You are analysing your project and have found there is a Cost Variance of -$40,866. What type of report is needed to report this to management?

A)  Progress report
B)  Exception report
C)  Forecasting report
D)  Trends report

Question 2

Delphi technique, Sensitivity analysis, and Monte Carlo Analysis are tools and techniques used as a part of which project task?

A)  Expert Judgement
B)  Reserve analysis
C)  Schedule Compression
D)  Quantitative Risk Assessment

Question 3

You are working in Risk Management and identifying the risks for a project. What document will be used to maintain and record information about risks identified and form appropriate responses?

A)  Risk Register
B)  Project Management Plan
C)  Tornado diagram
D)  Prompt lists

Question 4

You are working with the risk team in your project and are in the process of ranking risks for further analysis or action by assessing their probability of occurrence and impact. What is this called?

A)  Deep-dive Risk Analysis
B)  Subjective Risk Analysis
C)  Qualitative Risk Analysis
D)  Quantitative Risk Analysis

Question 5

You are wanting to brainstorm with your team to find and prepare a comprehensive list of risks in the project. Which of the following is not one of the types of information gathering techniques?

A)  Brainstorming
B)  Delphi technique
C)  Interviewing
D)  Sensitivity analysis

– See all the PMP Exam Questions –