Question 1

You are identifying the stakeholders in your project and need to analyse their engagement with a stakeholder engagement matrix. Which of the following is one of the types of Stakeholders?

A)  Executive
B)  Resistant
C)  Sensitive
D)  Passive

Question 2

You are working on managing stakeholder relationships in a project and identifying the stakeholders. What is something you will use as an input to this work?

A)  Work performance reports
B)  Change requests
C)  Approved change requests
D)  Agreements

Question 3

You have taken over a software development project 10 months after it started, and need to find out project stakeholders and roles. Which one of the following documents will provide the list of the project stakeholder to you?

A)  Project Management Plan
B)  Stakeholder List
C)  Stakeholder Register
D)  Identify Stakeholders

Question 4

There are many stakeholders in your project and you need to find out who is most likely to go above and beyond to help you. In your stakeholder analysis, what type of stakeholder are you looking for?

A)  Mature
B)  Saturated
C)  Superficial
D)  Leading

Question 5

You are working on a new project where the team is not working well together. You understand this as one of the five stages of team development that you will have to work through. Which of the following is NOT one of the stages of Team Development?

A)  Forming
B)  Initiating
C)  Storming
D)  Adjourning