PMP Exam Questions – Practice Session | 04

– See all the PMP Exam Questions – 

PMP Practice ExamPMP Exam Question Session 4

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

 

Question 1

Two team members in your project are having issues working together. You discuss this problem with the functional manager and jointly agree on a solution. What type of organizational structure are you working in?

A) Project oriented
B) Strong Matrix
C) Balanced Matrix
D) Weak Matrix

Question 2

A project management office (PMO) is a group or department that defines and maintains standards for project management within the organization. What is the primary objective of a PMO?

A) To support the customers receiving the product
B) To support the project managers
C) To support senior management
D) To support the industry

Question 3

You are working on an agile project as a project manager and performing sprint planning. You are planning the work in detail to be completed soon, and long term work is planned at a high level. What is this called?

A) Detailed Elaboration
B) Waterfall Planning
C) Agile Planning
D) Rolling Wave Planning

Question 4

At what stage of a project is a project manager typically assigned to a project?

A) The very beginning, during project initiation
B) The beginning to middle, during project planning
C) The middle, during project execution
D) The middle to end, during project monitoring

Question 5

You are in the process of identifying the methods your company uses to accept third party vendors and procure their services. What are you looking for?

A) Rating Selection Criteria
B) Source Selection Criteria
C) Scoring Selection Criteria
D) Proposal Selection Criteria

– See all the PMP Exam Questions –