PMP Practice Exam Questions 17PMP Exam Question Session 17

In this series we will walk through five PMP Practice Exam Questions each day – a great way to set up your morning as you prepare to pass the PMP Exam. It is also useful for the CAPM exam, as the content is very similar.

We will also figure them out together, and you’ll see the thought process behind solving these PMP exam questions.

I hope you enjoy!

Question 1

Estimate at Completion is the forecasted cost of the project as the project progresses. Your project has a budget of $10,000.
30% of the work has been completed against planned 30%, and $10,000 has been spent so far. If the CPI impacts our future cost, what is the Estimate At Completion (EAC)?

A)  $17,000
B)  $44,444
C)  $33,333
D)  $22,222

Question 2

You are working on a project and wanting to plan the immediate work in detail, while leaving the remaining work at a higher level. What are you doing?

A)  Executive Planning
B)  Rolling Wave Planning
C)  Progressive Planning
D)  Extra Planning

Question 3

You are working with your project team and wanting to stimulate creativity and new ideas. Which of the following is a group creativity technique you might use?

A)  Nominal group technique
B)  Regression analysis
C)  Tornado diagram
D)  Prompt lists

Question 4

As a project manager, you are wanting to work with the project sponsor to bring more objectivity to the acceptance process. What is this project activity called?

A)  Collecting Requirements
B)  Estimating Activity Durations
C)  Planning Schedule Management
D)  Validating Scope

Question 5

You are working through the scope of your project and wanting to decompose the high level features into smaller pieces of work that a team can deliver using a work breakdown structure. What is that level of the work breakdown structure called?

A)  Work Package
B)  Work Product
C)  Work Deliverable
D)  Work Task